Lagos State Governor, Babajide Sanwo-Olu, has assured motorists that the Opebi-Odoiya Alaro Bridge will be operational before the holidays, following delays in its completion.
The governor gave the assurance during a visit to the project site to assess progress and identify the reasons for the delay, after previously projecting that the bridge would open to traffic by the end of September.

Sanwo-Olu attributed part of the delay to the installation of a 25-metre steel monument designed to preserve the history of the Cane Village, which was formerly known for its cane market.
He explained that the monument features four hands weaving cane, symbolising the area’s heritage while serving as a new landmark along the corridor.
According to the governor, three of the four steel components have been assembled and fitted, while work on the final section is ongoing. He added that the monument was 80 per cent complete.
Sanwo-Olu stressed that safety remained a priority, noting that the road would not be opened until all sections of the structure were securely installed.
He acknowledged the inconvenience caused by the delay and appealed to motorists for patience, assuring them that the bridge would be ready before the holidays to improve traffic movement and enhance connectivity along the corridor.