The first phase of Kara Bridge repairs completed

The first phase of repair work on the Kara Bridge along the Lagos-Ibadan Expressway has been completed, bringing some relief to motorists who endured heavy traffic around the busy corridor in recent days.

The contractor handling the project completed the first phase of the concrete works on Wednesday, September 9, a day after the Federal Government began rehabilitating the bridge’s damaged expansion joints.

The two-week repair exercise is expected to continue until September 22. The work involves replacing worn-out expansion joints that have exceeded their service life and raised safety concerns for motorists using the bridge.

The commencement of the repairs on Tuesday triggered hours of gridlock, with traffic reportedly stretching from the Kara Bridge in Ogun State towards the 7Up area of Lagos. Many commuters were forced to spend several hours on the road as construction activities reduced the number of lanes available to traffic.

The Acting Controller of Works in Ogun State, Richard Adeleye, had explained that the repairs would be carried out in phases to keep traffic moving while the work continues.

According to him, contractors would work on one side of the affected section before moving to the other side. The approach is intended to limit disruption while ensuring that the damaged expansion joints are properly replaced.

Traffic flow improved somewhat following the completion of the first phase, although motorists have been advised to expect further delays around the construction area.

Traffic management and security agencies, including the Federal Road Safety Corps, Lagos State Traffic Management Authority and Ogun State Traffic Compliance and Enforcement Corps, have been deployed to manage vehicle movement and ease congestion.

Authorities have also appealed to motorists to remain patient, follow the instructions of traffic officials and plan their journeys with the ongoing repairs in mind.

The Federal Government said the intervention is aimed at improving road safety, preserving the structural integrity of the bridge and ensuring smoother movement along the Lagos-Ibadan Expressway.